LLC2 SPILL PLATE REPAIR
Monday, September 18, 2017
LLC2 CLEANING/WASHING AT CONVEYOR SIDE
LLC3 CLEANING/WASHING AT CONVEYOR SIDE
Sunday, September 17, 2017
LLC1 REMOVAL OF 1 FEEDER VIBRATOR MOTOR (6 SEPT 2017)
Friday, September 15, 2017
REMOVE RUST (BEFORE AND AFTER)
FAULTY/DAMAGE CONTACT DEVIATION LIMIT SWITCH 1 (P1011) UP CONVEYOR. BEFORE AND AFTER REPAIR
LAYOUT 580 & 620 TONNE FOR AUTO WEIGHING SCALE (CABINET A7)
Thursday, September 14, 2017
LLC2 MAKE TEMPORARY STAND FOR MAGNETIC DRILL
LLC2 SCREW SHAFT PIN INSTALLATION
LLC3 DRILL 12mm CENTER HOLE
Wednesday, September 13, 2017
LLC2 TO ADJUST DEVIATION MOUNTING ( FURTHER TO THE BACK)
LLC1, 2 & 3; TWISTED PAIR CABLE LAYOUT (Analog output)
LLC2 ADJUST AND CUT NEW RUBBER SKIRT
LLC3 REMOVING AND CLEANING (MANGANESE)